Salmonella Outbreak Shuts Down ‘World’s Largest’ Chocolate Factory in Belgium

Lorenz Duchamps
By Lorenz Duchamps
June 30, 2022Europe
share
Salmonella Outbreak Shuts Down ‘World’s Largest’ Chocolate Factory in Belgium
Employees walk at Barry Callebaut production site in Wieze, near Brussels, on June 30, 2022. (Kenzo Tribouillard/AFP via Getty Images)

An international chocolate factory has shut down all production at a plant in Belgium after discovering a salmonella-positive lot, the company confirmed on Thursday.

In a June 30 statement, the Swiss chocolate maker, Barry Callebaut, said all products manufactured since June 25 in Wieze, a village in East Flanders, have been placed on hold.

The company noted that they’re currently working on contacting all customers who may have received products impacted by the contamination.

At this point, it’s unclear how many, if any, products of the salmonella-positive lot have actually reached consumers, Korneel Warlop, a spokesman for Barry Callebaut, told AFP.

Warlop told the agency that most of the products discovered to be contaminated are still on the site.

Additionally, the factory has also asked customers to “block any shipped products” as a precaution.

“Barry Callebaut informed the Belgian food authorities (FAVV) about the incident and has taken the precautionary measure to stop all chocolate production lines and to block all products manufactured since the time of testing,” the company wrote on its website.

NTD Photo
The entrance of Barry Callebaut production site in Wieze, Belgium, on June 30, 2022. (Kenzo Tribouillard/AFP via Getty Images)

Quality experts identified lecithin as the source of the contamination, the company said. Lecithins is a yellow waxy substance and mixture of glycerophospholipids that is used for smoothing food textures and repelling sticking materials.

“As lecithin is used in all chocolate production, we have taken the precautionary measure to stop all production lines,” the chocolate maker said, adding that all products manufactured since June 25 will be placed on hold while the company continues to investigate the “root cause analysis and risk assessment.”

“Barry Callebaut will now take the time to continue with the very diligent root cause analysis—keeping the FAVV informed in the process,” it said. “When that is completed the lines will be cleaned and disinfected before resuming the production process.”

The company, which it says is the world’s largest chocolate factory that produces around 270,000 tons from bean to chocolate every year, described the incident as “a very exceptional case,” explaining that they were able to quickly identify the contamination because there are nearly two dozen employees working on food safety.

“In our local site in Wieze, we train our people to recognize food safety risks,” it said. More than 1,000 employees work at the Belgian factory, while international production reaches over 36 countries worldwide.

The discovery at the Wieze plant comes weeks after Ferrero Group was granted conditional authorization to restart its production lines in mid-June after Kinder products in the UK were recalled in April over an outbreak of salmonella at a Ferrero plant in Belgium.

NTD Photo
The Ardennes Ferrero factory in Arlon, Belgium, on April 8, 2022. (Erik Lalmand/BELGA/AFP via Getty Images)

Belgian health authorities ordered the Italian confectionery group to suspend all production at its plant in Arlon in late April after an investigation into dozens of cases of salmonella linked to the company’s Kinder chocolates.

“After Salmonella was detected in the Arlon plant, Ferrero has taken concrete actions to ensure that a situation like this does not happen again,” the company said in a June 17 statement announcing the restart of production lines.

“More than 1,000 Ferrero employees and independent specialists have been working at the plant continuously,” it explained. “More than 1,800 quality tests have been completed, 10,000 parts dismantled and cleaned, and significant investments made. This includes the replacement of multiple pieces of equipment as well as the installation of 300 meters of new pipeline.”